Equipment: 20 tons flake ice machine
Purpose: Concrete cooling
Project background introduction
The total investment of Maojun Reservoir Project is 2.789 billion yuan, which is composed of two parts: the hub project and the irrigation district project. The hub project is located in Lanshan County, Yongzhou City, Hunan Province. Large (2) reservoirs that are mainly used for irrigation, combined with water supply, and taking into account power generation. The normal storage level of the reservoir is 342.50 meters, the design flood level is 342.91 meters, the check flood level is 343.93 meters, the total storage capacity is 116.5 million cubic meters, and Xingli storage capacity is 92 million cubic meters.